Human Resource And Management

The Australian Grand Prix Event Analysis

Executive Summary

Organizing events, this same topic seems like a daunting task, as the late ’90s concept, which only attracted attention in India, was a key element needed to manage any type of event. Regardless of the type and size of the show, the mental and physical hard work is done only slightly differently. Although this term is relatively new in India, Indians held weddings, naming ceremonies, and interpreters long before independence. However, due to poor predictions and improperly processed ingredients, there are problems such as food waste or food poisoning as fewer people fall for Pandal. Turning an event into success or failure is very easy for most people. Only 5 minutes are exposed to evaluate an event, so 70-80 people spend nearly 3-4 months of effort to be productive or wasteful. Hence, their efforts are always on the line before the event date. There are lots of activities to do. First of all, the first step is to form a committee and assign different positions to each committee. Here, you will be aware of all the theoretical concepts that you have learned so far: public relations, human resource planning, logistics, human skills, control, accounting, and organization.

Introduction

The increasing number and importance of festivals is a worldwide phenomenon. Cultural experts, government agencies involved in cultural policy and financial decision-making, and the general public are attracted by the arts, as well as the social and economic backgrounds of the festival (Newell and Grashina, 2003). Event management is a fast-growing multi-billion dollar industry that regularly hosts major shows and events. Surprisingly, no formal survey has yet been conducted to assess the growth of this industry. Industries include MICE (Meetings, Promotions, and Events), Exhibitions, Conferences, Seminars, and different areas together with live music and wearing occasions. From an expert point of view, organizing events is a thrilling and interesting career that requires a lot of hard paintings and dynamism (PMP, 2014). The logistics facet of the enterprise pays less than the sales/sponsorship aspect. However, a few say they may be two one-of-a-kind industries.

The Objective Of The Project

The task is to lay, build and conduct a -week-long Park Art Festival, which is referred to as Beyond Walls. The finances for the whole project are $ hundred and fifty 000. The mission starts off evolving on September 15, 2020 and could end in July 2021. Work includes know-how of the necessities of the community and designing and imposing the event, which needs to be completed by June 30, 2021.

Project Scope

Our scope is to work with the network to get their comments, lay out the park, invite artists, and control this 2-week event, along with arranging the park and cleaning up after the event. The occasion will now include not only the works of art created by artists but also food, music, and other entertainment.

User Acceptance Criteria

All the coaching of the occasion consists of making plans, reviewing, and approving finished earlier than June 30, 2020.

The price range of all of the occasion’s training is no more than$150,000.

All the deliverables and evaluation techniques are authorized by the sponsor.

All information meets the specific necessities of the community and key stakeholders.

The activities will ultimately be two weeks long and include the selected artists, food carriers, track, and different leisure.

All the occasions’ agenda had been advised with the aid of enough instructors and together with the control course.

Project Boundaries Or Exclusions

The venture includes developing an included task plan that consists of the layout, creation, and implementation of the subsequent summer Park Art Festival for two weeks. In addition, it calls for us to pick out and orient the artists, select food providers, tunes, and other entertainment required for the competition. Also, competition operations may be managed, and a clean-up of the website can be accomplished online.

On the other hand, the task excludes:

  • The construction of the park
  • Logistics are involved in bringing the shipping containers to the site (Morris and Hough, 1987)

Acquiring funds, although a fund has been received for designing the event

Project Constraints

The constraints of the project are:

  • Time – This integrated project plan for this project is required to be done by December 13, 2020, so the project team can only work for a limited period of time. (Pressure of deadline)
  • Budget – The requirement to complete the project under the estimated cost is $ 150,000(USD). The project team has a limited budget to execute this project. (Sponsor imposed funding limits)
  • Schedule – Everything should be completed no later than June 30, 2020, which means the full implementation of the project, such as work completed, reviewed, approved, and ready

Resources – Inside and outside resources are limited (Turner, 2009)

Stakeholder Management Plan

The stakeholder’s management plan for the complete project is as follows:

Stakeholder NumberStakeholder NumberType of StakeholderStakeholder Expectation (s)Stakeholder Interest(s)Influence on Project Resultmanagement strategies/Method of Communication
 Position in the organization or role in the projectInternal or ExternalHigh-level needs or expectations for the project and/or productHigh/ Med/LowSupporter/Opposed/ NeutralStrategies and tactics to maximize positive stakeholder influence and minimize or neutralize negative stakeholder

Influence.

   Deliver the  positive stakeholder influence
1Tim Mills- Project SponsorInternalproject within the allocated budget, on the time and success criteriaHighSupporterand minimize or neutralize negative stakeholder

influence.

2Project ManagerInternalDeliver the project successfullyHighSupporterManaging the project/Weekly & Monthly Meetings
   Meeting with   
   project   
   stakeholder   
   Expectations and maintaining the project requirements  Assists the PM to build and deliver project goals with their

expertise/Daily & Weekly status

3Project TeamInternal MediumSupporterreport meeting
 Community

(Neighbor) Lynn

 The expectation is to attend the art festival and get informed about the piece of art.  Assists the PM in building and delivering project goals with their expertise/Daily & Weekly statue
4ResidentsExternal MediumNeutralreport meeting
   Provide gifts,  The project manager will be informing the vendors about the location of the event. Also,

director of the event will get the permits for them/ Phone calls

   souvenirs, and  
   food for people  
   Who will be  
5Vendors(merchandise)ExternalAttending the event.LowNeutral
6The cleaning staff of the eventExternalEnsure the cleanliness and tidiness of the meeting placeLowNeutralThe project team will be assigned the cleaning staff designated areas in order to clean up event location/Phone calls
7Mayor of Lynn – Judith F.ExternalThe major expectation is increasingMediumSupporterKeeping updated mayor about the project status report weekly
 Kennedy awareness of the city of Lynn   
8Event OrganizerExternalProvide support and ideas in event planning based on the

information provided by the project team

MediumSupporterConceptualizes the projected event from beginning to finish in accordance with the planned requirements/Daily & Monthly meetings
9Artists and performersExternalProvide entertainmentLowSupporterEntertain the event clients by performing songs, dances, or any form of stage entertainment/Phone calls & e-mails
10Lynn PD (or local authorities)ExternalFull inspection of the project and provide insights on the project’s impact on the community.HighNeutralPromotes the interests of the local community and provides provisions to the project/keeps them informed by phone calls
11Local news., tv channelExternalFocus on the event publicity and advertisementsLowNeutralProvides business exposure/keeps them informed by phone calls
12On-site information & guide teamExternalGuides will help people by providing information about the town, art and so on. Walking tours.LowNeutralGiving a presentation about the importance of the event/keeping them informed by phone calls
13Painting supplies (or other supportive venues or

facilitates we use)

ExternalSuppliers will be given decor requirements and thus facilitate

plans that may fit the projected event

LowNeutralThe decor team will be given tasks and requirements by the project team/ The project team will keep them informed through phone calls or on-site meetings as needed
14Founders of Beyond-walls Al WilsonInternalFull inspection of the project in general and working closely

with the project management

HighSupporterBring the project off the ground and invest resources to help the project to succeed/ Daily & Weekly meetings.
   Team to ensure all the requirements and tasks are explicit and built with compassion   
15Associate Director Pedro SotoInternalResponsible for event planning and directing the operation of the projectHighSupporterProvide overall inspection of the general process of the project and plan day-to-day operations of the project/ Daily & Weekly meetings
16Program Manager- Julia MidlandInternalResponsible for overseeing and offering direction and guidance to the project in generalHighSupporterCoordinates and oversees the project/Daily & Weekly meetings
17Program Coordinator- Doneeca ThurstonInternalResponsible for ensuring and monitoring the implementation of the eventHighSupporterManages and oversees event planning and implementation and provides an insightful report to the administration/Daily & Weekly meetings
18Security ServiceExternalEnsures and protects the assets and the safety of the event participantsMediumSupporterPatrols and monitors activities at the projected event to protect the asset and human safety/Daily & Weekly meetings
19Transport ServiceExternalRefers to transportation (e.g. vehicles)that carry event

Participants from one location to another.

MediumSupporterProvides transport service/keeps them informed by phone calls
20Regulators (e.g. Office of the Technical Regulators)ExternalEnsures the safety of the associated workers and property of this projectHighNeutralProvide general security to the aligned workers and properties of the projected event/keep them informed by phone calls
21Catering SuppliersExternalProvides food and drinks to the event on-siteMediumSupporterFood suppliers will be given an allergy list to ensure the safety and allergies of the food/keep them informed by phone calls
22Artists & performerExternalSources of artists that best fit theMediumSupporterInformation about the event will be given so the agency knows who to
 booking agency event  assign/keep them informed by phone calls
23Suppliers of light and sound equipmentExternalEnsures event lighting and sound supportsMediumSupporterLight and sound suppliers will be contacted once the theme of the event is settled/keep them informed by phone calls

Marketing Plan

AudienceResponsibleDelivery/ Method/ FormatDue Date / FrequencyCommunication TypeObjective of CommunicationDeliverable
Project Manager, Project TeamProject Sponsor – Tim MillsFace to FaceOnceProject Approval Meeting– Review the project plan

– Review the project requirements

– Review the project roles and responsibilities

-Project Plan

– Project Requirement lists

– Agenda

Project TeamProject ManagerFace to FaceOnce a weekWeekly Project Status Report– Understanding of the project expectations

– Project Overview

– Forecasting project budget and schedule

– Reporting project progress

– Project Scope Statement

– WBS

– Weekly project status report

– Agenda

Mayor of Lynn – Judith F. KennedyProject ManagerE-mailOnce a weekWeekly Project Status Report– Keeping the mayor informed about the project– Weekly project status report
Project Sponsor – Tim MillsProject ManagerE-mail, PhoneOnce a weekWeekly Project Status Report– Keeping the project sponsor informed about the project– Weekly project status report

Project ManagerEvent OrganizerE-mailOnce a weekNew ideas about the project– Providing support and information at the organizational level– Planned requirements list

– Project organizational plan

– Change request Form

Lynn Residents and CommunityEvent OrganizerNewspaper, Social MediaOnceAnnouncement of the Beyond Walls project– Informing the community and residents of Lynn about the project content– Fliers

– Newspaper
– Social Media Campaign

Vendors & Catering SuppliersEvent OrganizerE-mail, PhoneOnce a monthPre-commission Event Plan– Discuss the community expectations from the vendors

– Prepare the menu and cuisine

– Request list

– List of the goods

– Beverage menu

– Food Menu

Artists & PerformersEvent OrganizerE-mailOnce a monthPre-commission Event Plan  
Lynn PD and Security ServiceProgram Coordinator – Doneeca ThurstonFace to FaceOncePre-commission Event Plan– Provide provision for the Beyond Walls Project

– Monitors activities at the event and ensures people’s safety

– Safety requirement report

– Event safety guide

– Event safety checklist

Transportation ServiceAssociate Director- Pedro SotoE-mailOncePre-commission Event Plan– Plan to transportation pick up and drop off locations

– Provide the shuttle service

– The map of the shuttle service

– Pick up and drop off locations

RegulatorsProgram Manager- Julia MidlandFace to Face, E-mailBimonthlyRequired Permits– Project legal-side requirements

– Obtain the location of the event

– Local requirements

– Safety requirements

-Permission Document
Project Sponsor- Tim Mills, Project Team, Event OrganizerProject ManagerFace to FaceOnce, the last week of the ProjectProject Closure– Discuss the Roll-out Plan
– Review the feedback

– Meeting agendas

-Performance Review

– Lessons learned documentation

– Project closure report

Project Budget

Updated Cost Statement

For the Beyond Walls project, we applied the Bottom-Up approach for cost estimation. The allotted budget for the project is $150,000, and the allowed Contingency Reserve will be 10% of the project, which will sum up the entire budget at around $165,000. After the cost estimation performed by the project team, the initial estimated budget is $156,014, which is a little higher than the allotted budget but can be covered well within the Contingency Reserves (Morris and Hough, 1987).

The following table shows the Baseline Cost distribution according to the project phases:

PhaseBudget (USD)Duration (days)
Beyond Walls Project$156,014228.5
Event Initiation & Conception$16,85034
Event Definition & Planning$30,33228
Event Execution & Monitoring$103,696149
Event Closure$5,13611

The project estimates also involve the following fixed costs where the fixed amount will be paid to the respective companies while signing the contract (Jones, 2014):

ActivityCost (USD)Description
Sign Contracts (Artists)$5,000Confirming the artists with the Artists Management Company for the Murals. Here, the company will be paid all the fees in advance.
Sign Contracts (Entertainment)$3,500Here, the event fee will be paid to the Entertainment Company in advance.
Sign Cleaning Contract$3,500Here, the cleaning company will be paid the fixed fees in advance when signing the contract.

Cost Baseline Statement

The cost baseline of Beyond the Wall is used to estimate project expenses against the budgeted project expenses (Masterman, 2014). In this case, the currently estimated baseline of this project is $156,014, which exceeds the actual cost of $149,858 by $6,156 and the initial estimated budget of $150,000 by $14; however, this extra amount of cost can be covered by the 10% contingency reserves set at the beginning.

NameActualRemainingCostBaseline CostCost Variance
EVENT INITIATION & CONCEPTION$13,105$2,825.00

 

$15,930$16,850.00($920.00)
EVENT DEFINITION & PLANNING$0.00

 

20,816.00$20,816.00

 

$30,332.00

 

($9,516.00)

 

EVENT EXECUTION & MONITORING$0.00

 

 

$108,276.00

 

$108,276.00

 

 

$103,696.00

 

 

$4,580.00

 

EVENT CLOSURE$0.00

 

$4,836.00

 

$4,836.00

 

$5,136.00

 

($300.00)

 

The cost baseline will only be changed when there is a change or changes in the scope statement, which also means that the project plan was not well-structured and planned (Kerzner, 2002). In this case, if the 10% contingency reserves are approved by the sponsor, the project doesn’t require any immediate changes to the cost baseline (Goldblatt, 1997); reversely, if the contingencies are not approved, we may cut down the cost by reducing expenses in Event Execution phases were the following example activities are taking an excessive amount of cost:

NameBaseline Cost
Select Artists$2,520.00
Select and Confirm the Theme$4,920.00
Publish on Social Media and On-site Marketing$8,000.00

Work Breakdown Structure

The given schedule baseline leads to finishing this project no later than  June 30th, 2020, and the estimated baseline schedule is June 31, 2021, which is a day later than the projected finish date. Our team has two options: first, talk to the sponsor and ask for an additional day, or second, go back and reschedule our planned activities to make certain adjustments to fit the time frame (Parent and Chappelet, 2017). The following are the tasks whose duration could be revised and updated in the future:

NameBaseline Duration
Select Vendors20 Days
Select and Confirm the Theme12 Days
Sign Contract for Entertainment5 Days

Work Baseline Statement

The total estimated work baseline is 4,710.88 hours, which is greater than the actual completion hour of 4,449.68h by 261.2, which means the project team is not spending the right number of hours on their tasks.

Scope Baseline Statement

The project is to design and hold a two-week event about an art festival named Beyond Walls. The duration of the project is from Sep 19, 2019, to Jun 30, 2020. The project budget is about 150,000 US dollars. After the creation of the work breakdown structure, our major deliverables include community research, project management, event design, artist, food vendor, entertainment, event conduction, and clean-up. At present, after the cost and schedule estimation, the scope of the project has not changed.

Items that may lead to change and adjustment of project scope baseline:

  • After the scheduled cost estimation and submission, a one-day delay and an overrun of $6,014 were approved.
  • The sponsor adds additional requirements, such as the construction of the park environment during the event.
  • Sponsor requirements change, such as there being no need for entertainment activities other than art exhibitions.
  • Event delay due to weather and other uncontrollable reasons.
  • The sponsor’s budget has adjustment.

Gantt Chart

Task NameDurationStartFinish
BEYOND WALLS PROJECT228.5 daysThu 9/20/20Tue 8/4/21
Event Initiation & Conception34 daysThu 9/20/20Web 11/6/20
Community Research9 daysThus 9/20/20Wed 10/2/20
Stakeholder Register12 daysWed 10/2/20Fri 10/18/20
Project Charter8 daysFri 10/18/20Wed 10/30/20
Deliverable Checklist5 daysWed 10/30/20Wed 11/6/20
Event Definition & Planning28 daysWed 11/6/20Fri 12/13/20
Project Management18 daysWed 11/6/20Mon 12/2/20
Event Scope Management8 daysWed 11/6/20Mon 11/18/20
Event Budget Plan9 daysMon 11/18/20Thu 11/28/20
Event Schedule9 daysMon 11/18/20Thu 11/28/20
Event Risk Management Plan10 daysMon 11/18/20Fri 11/29/20
Event Communication Plan8 daysMon 11/18/20Wed 11/27/20
Kick-Off Meeting12 daysThu 11/28/20Fri 12/13/20
Event Execution & Monitoring149 daysMon 1/6/21Thu 7/30/21
Event Design115 daysMon 1/6/21Fri 6/12/21
Event Permits & License20 daysMon 1/6/21Thu 1/30/21
Artist Management29 daysFri 1/31/21Wed 3/11/21
Food Vendor Management27 daysThu 3/12/21Fri 4/17/21
Music/Entertainment22 daysFri 1/31/21Mon 3/2/21
Crowd Management7 daysWed 6/3/21Thu 6/11/21
Marketing & Promotions40 daysMon 4/21/21Fri 6/12/21
Event Conduction74 daysMon 4/21/21Thu 7/30/21
Event Orientation10 daysWed 5/21/21Tue 6/2/21
Event Set-up Plan5 daysWed 6/3/21Tue 6/9/21
Operations Management9 daysWed 6/10/21Mon 6/22/21
Beyond Walls Event21 daysTue 6/23/21Mon 7/21/21
Event Clean-Up74daysMon 4/21/21Thu 7/30/21
Event Closure11 daysTue 7/21/21Tue 8/4/21
Final Performance Report8.67 daysTue 7/21/21Fri 7/31/21
Event Success Evaluation11 daysTue 7/21/21Tue 8/4/21
Event Closure11 daysTue 7/21/21Tue 8/4/21

Risk Management Plan

A risk Management Plan is a formal procedure by which the team will systematically identify, assess and respond to risk factors. It basically concentrates on identifying and controlling circumstances or activities that have the potential to lead to undesirable change. The team will perform a continuous risk management method that involves four key processes: Risk identification, risk analysis, risk response planning, and risk monitoring and controlling. Each process includes various methodologies (Veal and Burton, 2015).

To determine and categorize risks during the risk identification process, we are using a risk breakdown structure (RBS) and brainstorming methodologies. For the risk analysis process, it is recommended to use both qualitative and quantitative analysis for risk identification and then prioritize the risks as High, Medium, or Low based on probability, impacts, and costs (Mikulskienė, 2014). The discussed method will facilitate the creation of a risk matrix to determine the severity of the risk.

Then comes a risk mitigation and controlling plan, which involves the process of developing actions and options to minimize threats and exploit opportunities based on the identified and analyzed risks. The risk response process involves defining the response strategy, planning corrective action, and contingency plans (Lewis, 1995). Finally, to control and monitor risks, the project team will work on change management and control processes. The change request has to be assessed by the project change experts and then approved/rejected depending on the cost-benefit analysis.

Contingency Reserve Policy & Request:

The contingency reserve policy and request are based on risk assessment and analysis. According to the risk management plan and risk register, we are ready to apply for a contingency amount for our project – Beyond Wall. After discussing the actual situation and referring to the historical data and similar projects, our project team has decided to apply for 10 per cent of the whole project as the contingency reserve; the amount is $15,000. The specific statement of the requested amount is as below.

In the project scope statement, the budget for the entire project is $150,000. However, according to previous project cost estimation and determining cost baseline, our initial estimated budget is $156,014, which exceeds the allowed project budget by $6,014. Thus, we have the risk of overspending. However, after requesting $15,000 as a team contingency reserve, the total budget of the project is $165,000, which means that the overspending risk of $6,014 can be covered. In addition, based on the cost baseline statement, after the actual allocation of the project budget is completed, our actual cost is $149,858, which is less than the allowed project budget of $150,000. Therefore, the contingency reserve can be used more for other project risks. That is, the risk for cost category can be well controlled in the contingency reserve that is requested to be 10% of the budget. For the project risk register, we can conclude that the risks of adopting the mitigate method in the risk response plan all require applying more money to transfer the risk to a third-party commitment when dealing with the issue caused by the risk, that is, hiring more professional analysts or experts to manage and adjust. Among them, the five risks closely associated with the contingency reserve are MF03 – failing to define the scope, MF04 – ambiguous expectations, MF05 – inaccurate estimates, MF08 – insufficient change management, and MF10 – shortfalls in resources. Meanwhile, the probabilities of MF03, MF04, MF05, and MF10 are low, and their impacts of them are high. At the same time, the probability and impact of MF08 are medium. Thus, their risk scores are not located in the high-risk range. When responding to those risks, the $15,000 contingency reserve is sufficient (Mulcahy, 2011). Additionally, because these risks are specific to the project’s scope, changes, and resource allocation, as well as involve internal management and communication of project team members, external estimators and experts may face a lack of understanding of the actual situation. Therefore, we are more inclined to rely on the internal members of the project team to respond and resolve the risks, and accordingly, there is no need for too many additional expenses. In other words, the chances of using the contingency reserve are very low.

Contingency Reserve Policies:

  • Using contingency reserve when facing an issue caused by risk.
  • The change control process is the way to apply contingency reserve.
  • The contingency reserve can only be used after submitting the application and obtaining approval from the sponsor and manager.
  • In general, changes and adjustments need to be proposed in the project status reports and wait for permission, but in the event of an emergency, the risk owner can directly report to the manager and mobilize the contingency reserve after manager approval. If the requested amount of money is large, the manager needs to report directly to the sponsor and use the contingency reserve after sponsor approval (Quinn, 2013).

Conclusion

The project manager and the project team will carry out tests at planned periods at some stage of the task to make certain all methods are being efficiently applied and achieved. The great supervisor will offer fine management each day and conduct technique audits on a weekly basis, monitor technique overall performance metrics, and guarantee all processes follow assignment and organizational requirements. If discrepancies are found, the fine supervisor will meet with the Project Manager and evaluate the diagnosed discrepancies. The Project Manager will schedule regularly occurring undertakings, control them, and report reviews. In these critiques, an agenda object will encompass a review of assignment techniques, any discrepancies and/or audit findings from the nice supervisor, and a discussion on process improvement tasks.

References

Goldblatt, J. J. (1997) Special events: best practices in modern event management. Van Nostrand Reinhold.

Jones, M. (2014) Sustainable event management: A practical guide. Routledge.

Kerzner, H. (2002) Strategic planning for project management using a project management maturity model. John Wiley & Sons.

Lewis, J. P. (1995) Project planning, scheduling, and control: A hands-on guide to bringing projects in on time and on budget. Irwin.

Masterman, G. (2014) Strategic sports event management. Routledge.

Mikulskienė, B. (2014) Research and development project management: study book.

Morris, P. W. and Hough, G. H. (1987) ‘The anatomy of major projects: A study of the reality of project management’.

Mulcahy, R. (2011) PMP Exam Prep: Rita’s Course in a Book for Passing the PMP Exam. RMC Publications, Inc.

Newell, M. and Grashina, M. (2003) The project management question and answer book. Amacom.

Parent, M. M. and Chappelet, J.-L. (2017) Routledge handbook of sports event management. Routledge.

Pmp, J. F. (2014) The project management answer book. Berrett-Koehler Publishers.

Quinn, B. (2013) Key concepts in event management. Sage.

Turner, J. R. (2009) The handbook of project-based management: leading strategic change in organizations. McGraw-Hill New York, NY.

Veal, A. J. and Burton, C. (2015) Research methods for arts and event management.

Cite This Work

To export a reference to this article please select a referencing stye below:

SEARCH

WHY US?

Calculate Your Order




Standard price

$310

SAVE ON YOUR FIRST ORDER!

$263.5

YOU MAY ALSO LIKE

GAPS Analysis

GAPS analysis portrays a significant framework for individuals to identify and achieve desired career goals. This four-step methodology, i.e. goals, abilities, perceptions and standards, inspires

Read More »